Read the site logistics plan

Start with the site logistics plan and the phasing drawing. The plan shows where the trailers, the wash stations, and the portable toilets will sit. It also shows the path a service truck can use.

A fixture that cannot be reached will not be serviced on schedule. Check whether the plan changes by phase. A single set of fixtures may work for the first year and fail when the site fills with trades.

Count each phase separately and note the move dates. The general conditions should follow the actual site, not a single snapshot.

Set the headcount basis

Use the labor plan to set the peak and average headcount for each phase. The fixture count follows the number of workers, not the total project value. Record the source of the headcount and the date it was taken.

A count that ignores the peak will understate the service. Some specifications or local rules set a minimum number of fixtures per worker. Read the requirement and apply it to the peak count.

If the rule uses a ratio, show the arithmetic. A code citation beside the line makes the quantity easier to defend.

Count fixtures and service frequency

Count the toilets, urinals, hand wash stations, and drinking water units as separate items. Each has a rental cost and a service frequency. A single portable toilet line hides the wash station and water cost.

Build the count by type and by phase. Service frequency depends on use and on the supplier. A busy site may need daily service while a small job can run weekly.

Read the supplier terms and the specification. Add the delivery, pickup, and extra service charges to the estimate. Those charges are easy to miss when only the monthly rental is counted.

Separate owner and contractor scope

The owner may provide a permanent facility, a trailer, or a connection to the site water. The contractor may provide only the portable units. Confirm the boundary before costing.

A facility that is assumed to be available can become a contractor cost after mobilization. Check the utility connection for the trailer and the wash station. Water, power, and sewer may come from a temporary source.

Add the connection and the hose or cable to the scope. The utility review should match the fixture plan.

Include water and power

Hand wash stations and drinking water need a supply and a waste path. Some units are self-contained while others need a hose and a drain. Confirm the type before counting the connection.

A self-contained unit has a different service cost than a plumbed one. Power may be needed for lighting, heating, or a trailer. Add the temporary circuit and the temporary power scope to the general conditions when the fixture depends on it.

A unit without power in winter is a schedule problem, not just a comfort issue. Carry the circuit even when the unit is rented.

Plan relocation by phase

Portable units often move as the work moves. Each move carries a pickup, a delivery, and a new setup. Count the moves in the phasing plan and cost them.

A single rental line rarely covers a project that relocates the units several times. Check the access and the pad at each new location. A unit on soft ground or a slope may need a base or a different placement.

Add the site prep to the move cost. The relocation plan should be reviewed with the superintendent before the bid is final.

Carry removal and cleaning

At the end of the project, the units are serviced, removed, and the area is cleaned. That closeout step is a real cost. Add the final service, the pickup, and any restoration to the estimate.

A missed removal can appear as a back charge. Check the contract for the condition required at turnover. Some owners require the area to be swept and washed.

Others require a receipt for the final service. Put the requirement in the closeout checklist and the cost.

Record the service assumption

Write the headcount basis, the fixture count, the service frequency, and the phase moves into the bid file. Note the supplier quote and its expiration. A reviewer should be able to rebuild the line without calling the estimator.

That rebuild is the test of a complete line. Use the OSHA sanitation guidance as a reference for the minimum provision, not as a substitute for the project specification. Keep the local requirement beside it.

The stricter rule controls the count. Record the source date so a later rule change is visible.

Close the service line before bid day

Bring the fixture count and the service frequency to the bid review as one line. The reviewer should see the peak headcount and the phase moves. Ask whether the owner provides any facility or utility connection.

A shared assumption is not a scope. Compare the supplier quote with the actual site access and the service route. A truck that cannot reach the unit will not service it on time.

Add any pad, base, or gate work to the cost. The quote should match the site conditions. Record the removal and cleaning duty in the closeout checklist.

A final service that is not scheduled can become a back charge. Keep the delivery and pickup receipts with the project file. The general conditions should close cleanly.

Temporary site services
ItemBasisCost driver
Portable toiletsPeak headcount and ratioRental and service
Wash stationsFixture type and water sourceService and supply
Drinking waterCrew size and weatherDelivery and cups
RelocationPhase planPickup and setup

Frequently Asked Questions

How many portable toilets does a site need?

The count follows the peak headcount and the applicable rule. Check the specification and the local requirement, then use the higher number for the estimate.

Is daily service always required?

Not always. Service frequency depends on use, weather, and the supplier terms. A busy site may need daily service while a small job can run weekly.

Who pays for the final cleaning?

The contract should say. If the contractor owns the area at turnover, include the final service and cleaning in the general conditions.