Map the utility boundary

Start by marking where the permanent service ends and the temporary service begins. The utility company, the owner, and the contractor may each own a different segment. Write the boundary on the site logistics sketch and name the responsible party.

A boundary that lives only in a conversation will move when the work starts. List the services the project needs during construction, including power, water, sanitary, heating fuel, and communications. Add any service the owner will provide and any service the contractor must arrange.

The list should cover the whole construction period, not just the first phase. Each line needs an owner and a source.

Estimate power demand

Build the power estimate from the equipment the schedule actually uses. List the tools, lifts, heaters, pumps, and temporary lighting by phase. Apply a realistic diversity factor rather than adding every nameplate together.

The result should support the size of the temporary service and the distribution plan. Include the cost of poles, trenching, cable, panels, and meters when the contractor provides them. Add the connection charge and the monthly service charge for the expected duration.

Do not forget the removal cost at the end of the job. A temporary service that stays connected after turnover becomes a surprise charge.

Water and sanitary

Estimate water for dust control, concrete curing, cleaning, and temporary facilities. The source may be a municipal meter, a hydrant permit, or a stored supply. Each source has a different cost structure and a different approval path.

Record the source and the permit requirement beside the quantity. Sanitary service usually means portable units, a holding tank, or a connection to an existing line. Count the units from the crew size and the duration, then add servicing and relocation.

Place the units where they can be reached without crossing active work. A plan that ignores access will need a costly change later.

Fuel and heating

Temporary heating can consume a large amount of fuel in a winter schedule. Estimate the heat load from the space, the enclosure, and the outdoor design condition. Then convert the load into fuel use and service frequency.

A rough calculation with stated assumptions is better than a single guessed allowance. Include the tank, the piping, the safety equipment, and the delivery charge. Add the labor to monitor and refill the system.

If the permanent system will be available earlier, record that assumption and the date it depends on. The estimate should show what happens if the date slips.

Separate temporary and permanent

Keep temporary utility costs in their own cost code so they do not disappear into general conditions. A separate code makes the total visible during the bid review. It also gives the project team a way to track the actual spend.

Mixed codes hide the very cost that tends to grow. Check that permanent utility work is not counted twice. The site package may include the service entrance, while the electrical trade includes the distribution inside the building.

Mark the split clearly on both scopes. A simple boundary note prevents a duplicate line in the summary.

State the release conditions

Before release, confirm the utility availability dates with the provider or the owner. Record the date, the contact, and the service address. Note any condition that would delay the connection, such as a transformer upgrade or a road permit.

The bid should carry a qualification when the date is uncertain. Add the temporary utility assumptions to the handoff note after award. The project team needs the same boundary, duration, and source information to buy the work.

A clear note shortens the setup period and reduces the chance of an early change order. The review is complete when the assumptions are written, not when the number is entered.

Coordinate with the schedule

Map each temporary service to the construction phase that needs it. The power demand for foundation work is different from the demand for finishes, and the service size may change between phases. A single service sized for the peak can be expensive to carry through the quiet months.

The schedule should show when each service starts and stops. Share the utility plan with the trades that will connect to it. A crew that expects power at a certain date needs to know the actual date and the available capacity.

A mismatch can force a generator rental that was never in the estimate. Record the coordination and the agreed dates in the logistics plan.

Track actual use

After award, compare the actual utility use with the estimate at each phase. A large difference may mean the equipment list was wrong, the schedule moved, or the service is losing energy. Investigate before the next estimate rather than waiting for the final cost report.

The comparison is the feedback loop for the allowance. Keep the utility invoices and the service records with the project cost file. The records show the demand, the duration, and the charges that the estimate tried to predict.

A future bid can use the history instead of a fresh guess. That history is more valuable when it is tied to the same cost code.

Check the connection requirements

Ask the utility provider what it needs before it will energize the temporary service. The list may include a load letter, a site plan, an inspection, and a deposit. Each item has a lead time that belongs in the schedule.

A service that is ready but not approved is not available. Confirm who will own the meter and the account during construction. The owner, the contractor, and a subcontractor may each have a different arrangement.

A mismatch can delay the connection or leave a charge with the wrong party. Record the account holder and the billing address in the plan.

Temporary utility review
ServiceBasisOpen condition
PowerEquipment list and diversity factorTransformer or connection date
WaterSource and permitHydrant or meter approval
SanitaryCrew count and durationUnit access and servicing
Heating fuelHeat load and enclosurePermanent system date

Frequently Asked Questions

Should temporary utilities be in general conditions?

They can be, but a separate cost code inside general conditions keeps them visible. The review needs to see the total and the duration without searching multiple packages.

Who confirms the utility availability date?

The estimator should request it from the owner or the provider and record the source. A date without a named contact is only an assumption.

How detailed should the power estimate be?

Detailed enough to support the service size and the monthly charge. List the major equipment by phase and state the diversity factor used.

Construction EstimatingConstruction EstimatingCost Support