Define the power boundary
Start by defining where temporary power begins and ends. The boundary may be the utility meter, a temporary service pole, or a generator supplied by another party. Each choice changes the cable, the protection, and the responsibility.
Write the boundary on the estimate summary before costing any distribution. Check whether the permanent electrical service will be available during construction. If it will, the temporary scope may be limited to distribution and protection.
If it will not, the estimate needs a full temporary service with its own capacity study. The two cases are not interchangeable. The plan should also identify who is allowed to connect and disconnect equipment.
Uncontrolled access to a temporary panel creates a safety risk and a maintenance problem. Name the electrical lead and the backup person in the bid. That clarity reduces confusion when the site is busy.
Size the load
List the major loads: lifts, welders, compressors, heaters, dryers, and office trailers. Add the small tools and lighting that run across the site. A load list with run times is more useful than a single connected-load total.
The peak and the diversity factor drive the service size. Check the voltage and phase required by each item, because a mixed list may need more than one distribution system. A welder on a long run may need a heavier cable to control voltage drop.
Record the assumption and the calculation basis. The estimate should show why the selected service is adequate.
Plan the distribution
Map the distribution from the source to the work areas. Include the main distribution panel, the subpanels, the feeders, and the branch circuits. Add the protection, grounding, and weatherproofing required for an outdoor or unfinished space.
The map should follow the actual site layout, not a generic typical. As the work moves, the distribution may need to move with it. A phased project can require several relocations, each with labor and downtime.
Record the moves in the plan and carry the labor. Compare the temporary layout with the site logistics estimate so the two documents agree.
Separate owner and contractor scope
The owner may provide the temporary service, the generator, or the fuel, while the contractor provides distribution and maintenance. The split must be explicit in the bid. Check the owner-furnished utility scope and record what is excluded.
An assumed owner connection can become a contractor cost after award. When the owner provides the source, confirm the capacity, the connection point, and the date it will be available. A source that arrives late forces a rental generator and a change.
State the dependency in the bid qualifications. The reviewer needs to see the date, not just the equipment.
Carry the operating cost
Temporary power carries operating cost beyond the initial installation. Fuel, maintenance, testing, and monitoring continue for the life of the service. Add those items to the estimate with a duration that matches the schedule.
A generator that runs for extra months is a real cost, not a rounding item. Include the labor to inspect and repair the distribution during construction. Cords and panels get damaged, and a fault can stop work in an area.
Set a response expectation and carry the standby time. Follow the estimating review practice of recording the service assumption beside the labor line.
Plan removal and closeout
Temporary power must be removed when the permanent service takes over. That step includes disconnecting, removing cable, patching, and returning rented equipment. If the removal is left out, the cost appears at the end when the budget is tight.
Add it to the bid with a clear trigger. Record the handover date and the person who will confirm the permanent service is reliable. A premature removal can interrupt commissioning and punch work.
Keep a small standby source in the plan until the permanent system is accepted. The closeout note should say who owns that decision.
Check grounding and protection
Temporary power needs grounding, overcurrent protection, and ground-fault protection that match the site conditions. An outdoor service may need additional protection for moisture and physical damage. The estimate should carry the devices, not only the cable.
A service that trips repeatedly costs more in downtime than in hardware. Inspect the available fault current and the breaker ratings before selecting the distribution. A mismatch can create a safety hazard and a failed inspection.
Record the basis for the selection and the person who reviewed it. The electrical subcontractor should confirm the design before the bid is released.
Coordinate with hot work and fire watch
Temporary power supports welders, cutters, and heaters that trigger hot work rules. The plan should show where those operations occur and how the power reaches them. A long extension run across a walkway is both a trip hazard and a voltage-drop problem.
Route the cable with the hot work plan in mind. Some sites require a fire watch during hot work, and the watch may need its own lighting and communication. Add that support to the temporary power scope when the project requires it.
Record the trigger and the duration. The electrical plan and the safety plan should not be written in isolation.
| Element | What to confirm | Estimate impact |
|---|---|---|
| Service boundary | Meter, pole, generator, or owner source | Defines the included scope |
| Load list | Major loads, small tools, and run times | Sets service capacity |
| Distribution | Panels, feeders, branch circuits, moves | Drives labor and cable |
| Removal | Date and restoration responsibility | Avoids closeout gap |