Build the underground utility connection point reconciliation record

Begin with the civil plans, utility profiles, surveys, and available utility-owner information. Mark each connection by system, drawing reference, station or grid location, elevation basis, and responsible package.

A line that disappears at a sheet edge is an open endpoint, not a complete takeoff. Use the site utilities takeoff review as a related control, but keep this takeoff tied to its own drawing population and cost lines.

Check quantities and scope conditions

Trace service entries, manholes, tie-ins, caps, valves, meters, and transitions between new and existing work. Record conflicts between plan and profile instead of choosing the easier view. Carry unanswered conditions in a clarification log with a visible estimate treatment.

AACE recommended practices provide general estimating references. The project documents and approved estimate basis control the actual quantity and scope decisions.

Underground Utility Connection Point Reconciliation record
Review fieldRequired record
PopulationLocation, type, and source
QuantityMeasured basis and unit
InterfaceIncluded work and package owner
DispositionEstimate treatment and reviewer

Reconcile the estimate before release

Reconcile every endpoint to the measured run and its excavation, bedding, backfill, testing, restoration, and temporary service scope. The record should show who verifies field conditions and which costs change if the assumed point moves. Close open assignments through the construction scope gap matrix and preserve the decision with the estimate revision.

Frequently asked questions

What starts a underground utility connection point reconciliation?

Start with the controlling plans, schedules, details, and specifications, then define the full item population before extending cost.

How should unclear scope be handled?

Record the assumption, current estimate treatment, responsible reviewer, and the source needed to resolve it.

What should remain with the estimate?

Keep the quantity record, source references, scope assignments, estimate revision, and approved disposition together.