Name the uncertainty

Describe the uncertain condition in project terms: incomplete design, unknown existing conditions, pending utility requirements, or unsettled logistics. Separate normal quantity development from discrete risks that may or may not occur. Avoid combining unrelated concerns into one row.

Specific entries make later removal or adjustment possible without reopening the entire estimate. Use the allowance drawdown log as a related estimate control.

Estimate exposure consistently

Record probability, cost impact or range, schedule consequence, and the calculation method approved by the company. Use the estimate allowance drawdown log when a defined allowance is more appropriate than contingency.

The AACE recommended practices discuss risk and estimate classification concepts. Apply them within the company's approved method and the project's actual level of definition.

How to Tie Estimate Contingency to a Risk Register review record
Review fieldRequired record
RiskSpecific uncertain condition
ExposureProbability and cost range
TreatmentContingency, allowance, or exclusion
OwnerNext decision and date

Review changes at each estimate issue

Close risks resolved by design, add newly discovered items, and prevent a transferred risk from remaining in two places. Compare the register total with the contingency carried in the estimate and explain any difference. Send open decisions into the estimate review comment resolution record so reviewer concerns receive a disposition before issue.

Frequently Asked Questions

What should be recorded first for how to tie estimate contingency to a risk register?

Specific uncertain condition should be recorded with the controlling project source and responsible estimator.

Who should resolve an open item?

Assign it to a named estimator or authorized reviewer and include the decision deadline.

What evidence should remain with the estimate?

Keep the source document, estimate treatment, revision, reviewer, and final disposition together.

Risk ReviewConstruction EstimatingCost Support