Read the roof plan and drainage notes

Start with the roof plan and the plumbing notes together. The plan shows drain locations while the notes set the size, material, and connection. A count taken from one sheet without the other can miss a secondary system.

Mark the governing detail on the takeoff sheet. Check the roof slope and the low points. A drain shown at a high point may be a vent or a future connection rather than a working drain.

Confirm the intent with the reflected ceiling plan or the roof detail. A misread symbol changes the count and the pipe route.

Count drains and scuppers

Count the primary drains, the secondary drains, and the overflow scuppers as separate items. Each type has its own body, strainer, and connection. A single drain count hides the overflow scope.

Build the count by roof area and by system. Include the parapet scuppers and the through-wall overflows shown on the elevations. Those items may be supplied by the roofing trade rather than the plumber.

Confirm the boundary and the material. A missed scupper can leave the roof without a secondary path.

Check the overflow path

The overflow system must discharge where the code and the design intend. That path may run through a wall, a downspout, or a separate leader. Trace it from the roof to the discharge point.

A path that crosses another trade is a coordination item, not just a pipe. Confirm the elevation difference between the primary and secondary inlets. The overflow must start before the roof load becomes unsafe.

Read the structural and architectural details for the required depth. Record the set point in the bid so the installer can verify it.

Review leader and conductor scope

Leaders and conductors carry the water from the roof to the storm system. Count the pipe, the fittings, the hangers, and the connections. Check whether the pipe is exposed, concealed, or buried.

Each condition changes the material and the labor. Confirm the connection point at the storm sewer or the retention system. The connection may belong to the site contractor.

Record the boundary and the invert elevation. A missing connection is a common gap between the plumbing and site packages.

Coordinate with roof insulation and crickets

Drain bodies and scuppers must fit the roof assembly, including insulation and the cricket. A deep drain may need a special body or a curb.

The roof transition review should show the interface with the membrane and the flashing. A mismatch at that interface is a leak risk and a rework cost.

Coordinate structural openings

Every leader that passes through a slab or wall needs an opening, a sleeve, or a curb. Those items may sit with the structural or architectural package.

Check the takeoff review for the opening count and the firestopping requirement. An opening discovered after the pour is a costly field fix.

Carry test and inspection cost

Roof drainage may require a water test, a smoke test, or an inspection before the membrane is closed. Add the labor and the water source. A test that fails can require a repair and a repeat.

The cost belongs in the plumbing or roofing package, not in contingency. Check whether the inspection must occur before the insulation or after the flashing. The sequence affects access and the amount of rework.

Put the milestone in the schedule and the estimate. A missed inspection can delay the roof close-in.

Document the boundary and close

Write the drain count, the scupper count, the leader material, and the connection point into the bid file. Note any item supplied by the roofing trade. A clear boundary prevents a duplicate or a gap at award.

Name the responsible party for each item on that boundary. Use the AACE recommended practices as a reference for documenting the scope basis. Keep the roof plan and the plumbing notes with the takeoff.

The reviewer should be able to follow the path from the roof to the discharge. A clear path also supports a fair comparison of the plumbing bids.

Use the roof plan in the bid review

Bring the drain and scupper count to the bid review with the roof plan open. The reviewer should see the primary path and the overflow path on the same sheet. Ask whether the roofing trade supplies any drain body.

A clear split prevents a duplicate or a gap. Compare the leader route with the structural and architectural drawings. A route that crosses a beam or a rated wall needs a sleeve and a firestop.

Update the opening count when the route changes. The roof is only as good as the path below it. Record the test requirement and the inspection milestone in the schedule.

A water test that is not planned can delay the membrane and the ceiling. Keep the test record with the closeout documents. The owner needs evidence that the drainage works.

Bring the overflow elevation and the discharge point to the closeout review. A secondary path that is blocked by a later wall or a screen no longer works. Verify it after the roof and the facade are complete.

A final check is cheaper than a flood call. Keep the approved submittals for the drains, the scuppers, and the leaders with the as-built drawings. A substitution made in the field should be recorded with its listing.

The maintenance file should show the exact products installed. That record supports the next repair and the warranty.

Roof drainage scope
ItemWhat to confirmEstimate effect
Primary drainSize, body, and strainerSets plumbing count
OverflowScupper or secondary drainAdds a second path
LeaderMaterial, route, and connectionDrives pipe and labor
OpeningSleeve, curb, and firestopMoves scope to structure

Frequently Asked Questions

Are roof drains always supplied by the plumber?

Not always. The roofing trade may supply the drain body and strainer while the plumber makes the pipe connection. Confirm the split in the specification.

How is the overflow elevation set?

The design sets it above the primary inlet and below the level that would overload the roof. Read the architectural and structural details and record the set point.

Should a water test be in the plumbing bid?

Include the test when the specification or the sequence requires it. The cost includes water, labor, and a repeat test if the first one fails.