Read the hardware sets

Start with the hardware schedule and the door schedule together. The hardware set names the items while the door schedule names the fire rating, the material, and the size. A set estimated without the door rating can miss a required closer or panic device.

Mark the set number on the takeoff. Check the finish and the function of each item. An exterior door may need a weather seal, a threshold, and a sweep.

Those items may sit in the set or in the frame scope. A missing weather seal is a small cost that becomes a leak and a callback.

Match sets to the door schedule

Match every door to a hardware set and every set to at least one door. A set that is listed but unused is a costing error while a door without a set is a gap.

Resolve both before the bid. The takeoff review should show the count by set and by door type.

Check electrified hardware

Electrified hardware includes electric strikes, magnetic locks, request-to-exit devices, and power supplies. Each item needs power, a circuit, and a control interface. The hardware set may list the device without the electrical scope.

Confirm the boundary with the access control package. Count the power supplies and the circuits. A door that is far from the panel may need a dedicated run or a local power supply.

The electrical review should confirm the panel space and the pathway. A door that is far from power needs that cost in the same line.

Review frame and door preparation

Each hardware item needs a prep in the door or the frame. Some preps are standard while others are special and must be ordered with the frame. A field prep after the frame is set can void a fire rating or a warranty.

Confirm the prep before the order is released. Check the frame type and the anchor. A masonry frame has different prep and installation than a hollow metal frame in a drywall partition.

The labor and the lead time change with the frame type. Record the type in the takeoff.

Count keying and access control

Keying is a separate scope from the hardware supply. The owner may require a specific keyway, a construction key, and a final keying schedule. Count the cylinders and the keys, and confirm who provides the keying service.

A keying allowance that is too small can become a change. Access control adds card readers, controllers, and software. The hardware package may supply the reader while the security contractor supplies the controller.

Confirm the split and the cable. A reader without a controller is not a working door.

Carry installation labor

Installation labor depends on the door count, the hardware count, and the access. A set with many items takes longer than a basic passage set. Add the labor for each item and the time to adjust the door and the closer.

A door that does not latch is a callback. Check the sequencing with the frame and the drywall. A door installed before the wall is finished may be damaged and need a replacement.

The work package review should show the installation window. A premature install risks damage and a replacement.

Confirm fire ratings

A fire-rated door needs a rated frame, rated hardware, and a rated closer. The label and the listing must match the assembly. A substitution that is not listed can fail the inspection.

Check the rating on the door schedule and the hardware submittal. Some hardware items are not permitted on a fire door, such as a hold-open that is not listed for the application. Confirm the function and the listing.

A field change after inspection is expensive and may delay occupancy. Check the label before the door is hung, not after.

Document substitutions

When a specified item is unavailable, the substitution must be equal and approved. Record the proposed item, the reason, and the approval date.

The value engineering log should show the cost effect of the change. Keep the approval with the submittal package.

Record the package boundary

Write the set count, the electrified items, the keying scope, and the frame prep into the bid file. Note who supplies the access control and who installs it. A clear boundary prevents a duplicate or a gap at award.

List the supplier for each item. Use the ASPE references as a reference for the opening conventions used in the schedule. Keep the door schedule and the hardware schedule with the takeoff.

The reviewer should be able to trace every set to a door. That trace is the proof the package is complete.

Close the hardware package before bid day

Bring the hardware schedule and the door schedule to the bid review together. The reviewer should see every set and every rated opening. Ask whether the electrified items include power and control.

A set that stops at the reader is not a working door. Compare the frame prep with the frame type and the wall construction. A special prep that is discovered late can delay the frame order.

Update the lead time when the hardware changes. The opening schedule should reflect the real delivery path. Record the keying and access control split in the bid file.

A cylinder without a keying schedule is an incomplete deliverable. Keep the approved submittals with the estimate. The closeout package should show every door and every key.

Exterior hardware review
ItemWhat to confirmEstimate effect
SetFunction and finishSets material cost
ElectrifiedPower, circuit, and controlAdds electrical scope
Frame prepStandard or specialChanges lead time
KeyingKeyway and cylindersAdds a service line

Frequently Asked Questions

Who supplies the access control reader?

The contract may assign it to the hardware supplier or the security contractor. Confirm the supply and the installation boundary before costing.

Can a standard closer be used on a fire door?

Only when it is listed for the assembly and the rating. Check the door schedule and the submittal rather than assuming a standard item is acceptable.

How is keying usually handled?

Keying is often a separate service from the hardware supply. Count the cylinders and the keys, and confirm whether the owner or the contractor provides the keying.