Write risks as project conditions

Describe the uncertain event or condition, its cause, and the estimate consequence. Avoid labels such as coordination risk with no context.

Cite the drawing, specification, quote, schedule, site observation, or missing decision that supports the entry. Begin with the weather risk estimate and keep ordinary checklist completion separate from genuine uncertainty.

Show the current cost treatment

Record affected estimate codes, quantity or time exposure, current allowance or contingency treatment, exclusions, and sensitivity where supportable. Do not add several overlapping percentages for the same uncertainty.

Make correlations and shared causes visible to the reviewer. AACE materials on risk analysis provide professional reference points, but the project team must select methods appropriate to its estimate and available evidence.

Assign decisions and close evidence

Give each open item one owner, a next action, a due date tied to bid or estimate milestones, and an escalation path. Status should distinguish open, monitoring, treatment approved, transferred, and closed. Closing an item requires retained evidence and an updated estimate where applicable.

Report material exceptions during the bid day estimate review. Archive the final register with the basis of estimate so downstream teams can see which uncertainty was included, excluded, or still open.

Estimate risk register fields
FieldPurpose
ConditionSpecific uncertainty and cause
EvidenceCurrent project source
ExposureAffected scope, cost, or time
TreatmentIncluded, excluded, allowed, transferred
OwnerAction, due date, closure evidence

Frequently asked questions

Is every open task an estimate risk?

No. Record uncertainties with a plausible scope, cost, or schedule consequence.

Should risks be hidden inside contingency?

No. Preserve the basis and avoid overlapping treatment.

When is a risk closed?

When resolution evidence is retained and the estimate treatment is updated or approved.