Read the access plan first
Start with the route from the public road to the lift position and mark every obstruction. Check the gate width, the turning radius, the overhead lines, and the pavement capacity. A crane that cannot reach the site cannot perform the work regardless of its chart.
Record the route and the obstructions on the same sketch. Confirm the delivery and assembly area for the crane and its counterweight. Large crawler cranes may need a separate transport and a longer assembly window.
The access plan should show where those operations happen without blocking the site. If the area is not available, the equipment choice changes.
Confirm size and reach
Build the lift plan from the load weight, the radius, and the boom length. Add the rigging, the hook block, and any lifting beam to the load. Compare the result with the crane chart at the actual configuration.
A chart value without the configuration is not a plan. Check the maximum radius for the farthest pick, not only the heaviest pick. A crane that handles the heavy load near the base may not reach the far corner.
Walk the lift sequence and note every position. The highest demand governs the equipment size.
Check ground conditions
Ask for the geotechnical information and the buried utility survey at the lift positions. The outrigger or track pressure must be supported by the ground or by a designed mat. A thin slab or a filled area may require a mat, a spreader, or a different location.
Record the assumed bearing capacity and the source. Include the cost of mats, cribbing, and any ground improvement in the estimate. Those items are easy to leave out because they belong to the crane package but not to the crane rental.
Add the labor to place and remove them. A ground failure is far more expensive than the support.
Plan rigging and laydown
List the rigging gear, the lifting points, and the person responsible for the lift plan. The estimate should carry the cost of the gear, the inspection, and the qualified lift director. A lift that needs a custom beam or a spreader frame adds fabrication time.
Record that time in the schedule. Laydown space is part of the lift plan because the crane must pick from somewhere. Show the staging area, the delivery sequence, and the path to the pick point.
A crowded site may need a second crane or a different erection sequence. The estimate should include the cost of the chosen sequence.
Coordinate with the trades
Share the lift plan with the trades that will work near the crane. The steel, mechanical, and curtain wall packages may all need the same window. A conflict in the schedule can leave the crane idle while the crew waits.
Record the coordination meeting and the agreed sequence. Check the shutdown or permit requirements for work near the public way. A crane over a sidewalk or a lane may need a permit, a flagger, or a police detail.
Add those costs to the crane package. The permit lead time also belongs in the schedule.
Record the hold points
Write the conditions that must be true before the lift proceeds. The list might include the mat installation, the ground verification, the permit, and the rigging inspection. Each condition needs an owner and a date.
A hold point without an owner is only a hope. Add the crane assumptions to the bid qualifications and the handoff note. State the configuration, the ground basis, and the access route.
If the site changes, the team will know which assumption to reopen. The review is complete when the lift plan and the estimate tell the same story.
Confirm the operator and crew
Confirm that the crane operator and the rigging crew are qualified for the lift and the equipment. Ask for the certification and the experience on comparable picks. A crew that has not worked with the crane model may need extra time for setup and rehearsal.
That time belongs in the schedule and the estimate. Identify the lift director and the signal person before the lift plan is final. The roles should be named rather than assigned on the day of the pick.
A clear chain of command reduces the chance of a miscommunication during the lift. Record the names and the contact information in the plan.
Review the lift schedule
Place each lift on the schedule with the date, the duration, and the crane configuration. A lift that depends on another trade's completion should show that dependency. A schedule that treats every lift as a single event hides the setup and relocation time.
The estimate should include the full crew day, not only the pick. Check the wind and weather limits for the crane and the load. A lift that is planned for an exposed season may lose days to wind.
Build a weather allowance into the schedule and the cost. The allowance should be visible rather than buried in a general contingency.
Document the final plan
Attach the final lift plan, the crane chart, the ground support calculation, and the permit to the estimate file. A reviewer should be able to see the basis for the equipment choice without calling the crane company. Note the date of each document and the revision used.
A plan without its basis is only a schedule. Send the plan to the project team with the handoff package. The team will need the configuration and the hold points when it books the crane and prepares the site.
A clear handoff reduces the chance that the plan is rebuilt from memory. The estimate and the field plan should start from the same document.
| Check | Question | Record |
|---|---|---|
| Access | Can the crane reach and set up? | Route sketch |
| Reach | Does the chart cover the farthest pick? | Lift plan |
| Ground | What supports the outriggers? | Geotechnical note |
| Rigging | Who owns the gear and the lift? | Gear list and director |